Anthropic’s Data Centres Will Run on 87% Gas by 2028, Study Finds

Key Takeaways

  • A case study published on 16 November 2026 estimates that about 87% of Anthropic’s power will come from gas and 11% from coal in 2028.
  • Anthropic had contracted 15 GW of compute as of October 2026, with about 5.9–9.6 GW contracted to specific data centre sites.
  • Total carbon dioxide emissions from Anthropic’s power use at these sites could reach 17–38 million metric tons of CO2 equivalent per year in 2028, with a mid-case of 32 million tons.
  • That mid-case is more than all of California’s power plants emitted in 2024, at 31.1 million tons, and more than the combined Scope 2 emissions reported for Meta, Microsoft and Google in 2025.
  • About 25% of Anthropic’s contracted power, 2.5 GW, comes from on-site gas generation, and 80% of that on-site capacity uses older-style simple-cycle turbines and engines.
  • The study estimates yearly health damage from air pollution at $2bn–$3bn, and estimates average carbon intensity at 1,033–1,076 lb CO2e/MWh, about 35% higher than the US grid average of 767.
  • The figures are estimates, not measurements, and the range reflects genuine uncertainty about how hard the data centres run.

What the Study Found

The Better Data Center Project, a nonprofit started by two former US Department of Energy officials, published a case study on 16 November 2026. The case study is titled “How AI is powered: a breakdown of BYOP and grid power”, and it analyses Anthropic’s compute commitments site by site. The focus is not on a single building or a single contract. It is on the pattern that emerges when Anthropic’s commitments are brought together and examined as a whole, and on what that pattern means for the source of the electricity that will power the company’s artificial intelligence systems in 2028.

The central finding is stark, and it is worth stating plainly at the outset. The study estimates that about 87% of Anthropic’s power will come from gas and 11% from coal in 2028. Those two figures, taken together, describe a power mix that is dominated by fossil fuels. The study counts both on-site gas and the grid plants likely to meet the added load, which it describes as marginal generators. In other words, the estimate is not limited to the power plants that Anthropic owns or operates directly. It also includes the power plants on the wider grid that are likely to increase their output in response to the additional demand created by Anthropic’s data centres.

The Scale of Anthropic’s Compute Commitments

Fifteen gigawatts is a difficult figure to hold in mind without a point of comparison, and the study does not ask the reader to treat it as a small or incidental number. It is the total of Anthropic’s contracted compute as of October 2026, and it is the starting point for everything else in the case study. The study then narrows that total to the portion that can be tied to specific data centre sites, about 5.9–9.6 GW, and it is on that site-specific portion that the detailed analysis of power sources and emissions is built.

The site-by-site approach is also important for a second reason. Data centres are not interchangeable. They sit in different places, they draw on different grids, they use different forms of on-site generation where they use it at all, and they are subject to different local conditions. A national average, or a company-wide average, can hide those differences. By analysing Anthropic’s compute commitments site by site, the study is able to build up a picture that reflects the particular mix of grid power and on-site power at each location, rather than assuming that every site looks the same.

Bring Your Own Power, Explained

One of the key ideas in the case study is “bring your own power”, often shortened to BYOP. The phrase describes a situation in which a data centre does not rely only on the grid for its electricity, but brings its own generation to the site. In Anthropic’s case, the study estimates that about 25% of its contracted power, 2.5 GW, comes from on-site gas generation. That is, about a quarter of the contracted power is met by gas generation located at the data centre site itself, rather than by electricity drawn from the wider grid.

There is a further detail about the on-site generation that the study draws attention to. About 80% of that on-site capacity uses older-style simple-cycle turbines and engines rather than modern combined-cycle plants. The study presents that as a characteristic of the on-site fleet, and it is a detail that matters to the overall picture because the type of plant affects the emissions associated with each unit of electricity generated. The study does not, in the material provided for this article, present a separate emissions figure for simple-cycle plant as against combined-cycle plant, and this article does not invent one. The point that can be made, on the basis of the study alone, is that the on-site gas fleet is largely made up of the older-style plant, and that this is part of the reason the study’s carbon intensity estimate is as high as it is.

The scale of the on-site gas commitment is also underlined by a separate purchase described in the study. The study says Anthropic recently bought commitments for 1.7 GW of heavy-duty gas generators for $3.4bn. That is a large commitment in its own right, and it sits alongside the estimate that 2.5 GW of contracted power comes from on-site gas generation. The two figures are not the same, and they should not be confused. One is a purchase of generator commitments, measured in gigawatts and in dollars. The other is an estimate of the share of contracted power met by on-site gas generation. What they have in common is that they both point in the same direction: towards a substantial and deliberate reliance on gas generation located at or near the data centres themselves.

87% Gas and 11% Coal in 2028

The headline estimate, that about 87% of Anthropic’s power will come from gas and 11% from coal in 2028, deserves careful reading. It is an estimate for a future year, not a measurement of power use in the past. It is based on the contracts and commitments that were in place as of October 2026, and on the study’s modelling of which plants are likely to meet the added load. It is also, as the study makes clear, an estimate that counts on-site gas and marginal grid generation together, so that the full fossil-fuel footprint of the added demand is captured, rather than only the portion that is most visible.

The two percentages together account for almost all of the power in the estimate. Gas dominates, at about 87%, and coal accounts for a further 11%. The study does not, in the material provided for this article, assign a precise percentage to every other source in the mix for 2028, and this article does not fill that gap with a guess. What can be said is that the estimate leaves little room for renewable sources in the power mix for that year, on the basis of the commitments and modelling described in the study. That is consistent with the study’s separate finding on renewable energy, which is set out in the next section.

No Direct Renewable Commitments in the US

Alongside the fossil-fuel figures, the study makes a finding about renewable energy that is central to understanding why the gas and coal shares are so high. The finding is that Anthropic has made no direct commitments to renewable energy in the US. Its only publicly disclosed renewable commitments, contracts or investments are in Norway and Canada, as of November 2026. That is a precise and limited claim, and it is important to reproduce it in those terms.

The claim is about direct commitments in the US, and about publicly disclosed commitments elsewhere. It does not say that Anthropic has no interest in renewable energy, and it does not say that the company has ruled out renewable energy in the future. It says that, as of November 2026, the only publicly disclosed renewable commitments, contracts or investments are in Norway and Canada, and that there are no direct commitments of that kind in the US. The distinction between the US and the two other countries named is part of the finding, and it is the US position that is most relevant to the power mix for the data centres analysed in the study, which are the sites to which Anthropic’s compute is contracted.

Anthropic’s own position, as quoted in the study, is that it is “working to broaden our energy mix with geothermal, wind, solar, and emerging technologies”. That sentence is the company’s own description of its direction of travel, and it names four categories: geothermal, wind, solar, and emerging technologies. The study does not, in the material provided for this article, set out a timetable for that broadening, or a set of contracts that would deliver it, or a figure for how much of the power mix would change as a result. This article therefore does not add a timetable or a figure of its own. The quoted sentence is presented here as the company’s stated intention, and the study’s finding about the absence of direct renewable commitments in the US is presented as the position as of November 2026.

Emissions: 17–38 Million Metric Tons in 2028

The study’s emissions estimate is the figure that is most likely to be quoted, and it is also the figure that needs the most careful handling. Total carbon dioxide emissions from Anthropic’s power use at these sites could reach 17–38 million metric tons of CO2 equivalent per year in 2028. The mid-case is 32 million tons. The range is wide, and the width is deliberate. It reflects genuine uncertainty about how hard the data centres run, and the study is explicit that the figures are estimates, not measurements.

The range should be read as a range, not as a choice between a low figure and a high figure. The low end, 17 million metric tons, and the high end, 38 million metric tons, are both within the study’s modelling, and the mid-case of 32 million tons sits towards the upper part of the range rather than in the middle of it. That positioning is itself informative, because it suggests that the study’s central view is closer to the high end than to the low end, even though the full range remains wide. This article does not narrow the range further, and it does not present the mid-case as a prediction that the actual figure will be exactly 32 million tons. It presents the mid-case as the study’s mid-case, and the range as the study’s range.

The unit used in the study is metric tons of CO2 equivalent per year, and the scope is the carbon dioxide emissions from Anthropic’s power use at the sites analysed. That scope is important. It is not a figure for the company’s total emissions from every activity, and it is not a figure for the emissions of the data centre industry as a whole. It is a figure for the power use at the sites to which Anthropic’s compute is contracted, in 2028, on the basis of the study’s modelling.

More Than California’s Power Plants in 2024

To help readers grasp the scale of the mid-case, the study makes a comparison with California. The mid-case of 32 million tons is more than all of California’s power plants emitted in 2024, which the study puts at 31.1 million tons. The comparison is between a single company’s power use at a set of data centre sites in 2028, on the mid-case estimate, and the total emissions from all of the power plants in California in 2024. That is the comparison the study makes, and it is a striking one, because California is a large state with a large power system, and the figure for its power plants in 2024 is a total for the whole state.

The comparison works because it puts an abstract figure, 32 million metric tons of CO2 equivalent per year, into a context that many readers will recognise. A figure in millions of tons can be hard to picture on its own. A comparison with the power plants of a whole state gives it a scale. The study’s point is not that Anthropic’s data centres are located in California, or that they draw their power from California’s grid. The point is one of scale: the mid-case for Anthropic’s power use at the sites analysed is larger than the total for California’s power plants in 2024.

More Than Meta, Microsoft and Google Combined

The study makes a second comparison, this time with three other large technology companies. The mid-case of 32 million tons is more than Meta, Microsoft and Google’s combined Scope 2 emissions from 2025, which the study puts at 5.9, 12 and 15 million tons respectively, location-based, before renewable offsets. The three figures add up to 32.9 million tons, which is close to the mid-case of 32 million tons, and the study’s wording, as provided for this article, is that the mid-case is more than the combined figure. This article reproduces the study’s comparison as stated, with the individual figures as given, and does not recalculate the comparison or substitute a different total.

That detail about the basis of the comparison matters, because Scope 2 figures can be reported in more than one way, and the choice of basis affects the result. By stating that the figures are location-based and before renewable offsets, the study is making clear which basis it is using, and it is using the same basis, in effect, for the comparison with Anthropic’s estimated emissions. The Anthropic figure is an estimate of the emissions from power use, based on the marginal generators likely to meet the added load, and the comparison is with the location-based Scope 2 figures for the three other companies.

Carbon Intensity 35% Above the US Grid Average

The study also presents a figure for carbon intensity, which is a measure of how much carbon dioxide is emitted for each unit of electricity generated. The average carbon intensity for Anthropic’s power is estimated at 1,033–1,076 lb CO2e/MWh. That is about 35% higher than the US grid average of 767 lb CO2e/MWh, using the same unit. The comparison is therefore between the study’s estimate for Anthropic’s power mix and the average for the US grid as a whole.

Carbon intensity is a useful measure because it captures the cleanliness, or otherwise, of the power mix in a single figure. A higher carbon intensity means that each megawatt-hour of electricity is associated with more carbon dioxide. A lower carbon intensity means that each megawatt-hour is associated with less. The study’s estimate, at 1,033–1,076 lb CO2e/MWh, is higher than the US grid average of 767, and the study quantifies that difference as about 35% higher.

The reason for the difference is the power mix described earlier in this article. A mix dominated by gas and coal will have a higher carbon intensity than a grid average that includes a wider range of sources, including sources with lower or zero emissions. The study’s estimate for Anthropic reflects the dominance of gas and coal in the marginal generation and on-site generation that make up the company’s power mix, and the 35% figure is a way of expressing how much higher that intensity is than the US average.

Health Damage Estimated at $2bn–$3bn a Year

The study does not limit itself to carbon dioxide. It also estimates yearly health damage from air pollution at $2bn–$3bn. That figure is presented as an estimate of the health damage associated with the air pollution from the power generation that supplies Anthropic’s data centres, and it is a yearly figure, in dollars, for the same period as the emissions estimates.

The figure is a monetary estimate of health damage, and it should be read as such. It is not a count of cases of illness, and it is not a figure for the number of people affected. It is an estimate, in dollars per year, of the damage to health caused by air pollution, and the study presents it as a range, $2bn–$3bn, rather than as a single figure. The range reflects uncertainty in the modelling, in the same way that the emissions range reflects uncertainty about how hard the data centres run and about the power mix.

The Named Sites: Colossus 2 and Nscale’s Monarch Campus

The study names two sites in particular, and they give a concrete shape to the figures above. Anthropic uses compute at SpaceX’s Colossus 2 facility, which still runs largely on temporary, unpermitted gas turbines, and it will draw up to 600 MW from Colossus 2 by the end of 2026. The description of the turbines as temporary and unpermitted is the study’s description, and it is presented here in those terms. The figure of up to 600 MW is the amount Anthropic will draw from the facility by the end of 2026, on the study’s account.

The second named site is Nscale’s Monarch Compute Campus in West Virginia. Anthropic contracted 460 MW from the campus, which is powered by reciprocating gas engines with significant formaldehyde and hazardous air pollutant emissions. That description, again, is the study’s, and it links the power source at the site directly to the air pollution discussed in the health damage estimate. The campus is a reminder that the wider debate about AI data centres and carbon emissions is not only about carbon dioxide. It is also about the other pollutants that come from the same generation, and about the people who live near the plants that produce it. The recent news that Nscale has halted hiring in a cost-cutting move is a separate development from the power arrangements at Monarch, and this article does not link the two beyond noting that both concern the same company.

Totals Could Keep Growing Towards 2030

The figures for 2028 are not presented in the study as a final total. Totals could keep growing, possibly doubling by 2030, as some analysts expect Anthropic to secure 30 GW by 2030. That expectation is attributed in the brief for this article to some analysts, and it is presented here on that basis. It is not presented as the study’s own forecast, and it is not presented as a commitment made by Anthropic. It is an expectation held by some analysts that the company could secure 30 GW by 2030, which would be double the 15 GW contracted as of October 2026.

How the Study Reached Its Figures

The study’s methodology is set out in the brief for this article in outline, and it is worth reproducing that outline here. The authors used the EPA’s AVERT tool to model marginal emissions, accounted for power usage effectiveness and utilisation rates, and published their full dataset. The use of AVERT, a tool from the US Environmental Protection Agency, is the basis for the modelling of marginal emissions, which is the modelling that produces the estimates of which grid plants are likely to meet the added load.

What We Could Not Verify

  • Actual measured emissions from Anthropic’s data centres in 2028, as opposed to the study’s estimates, which are based on modelling and on the contracts in place as of October 2026.
  • How hard the data centres will actually run, and therefore where within the 17–38 million metric ton range the true figure for 2028 will fall.
  • Whether Anthropic will secure 30 GW by 2030, as some analysts expect, and what the emissions figure for 2030 would be if it did.
  • Any timetable or contracted figure for Anthropic’s stated intention to broaden its energy mix with geothermal, wind, solar and emerging technologies.
  • A breakdown of the $2bn–$3bn yearly health damage estimate by pollutant, site or population.
  • Whether the Scope 2 comparison with Meta, Microsoft and Google would look different on a market-based basis or after renewable offsets, beyond the location-based figures given in the study.
  • Any response from Anthropic beyond the quoted sentence about broadening its energy mix, and any further detail on the renewable commitments in Norway and Canada.

Why This Study Matters

The Better Data Center Project’s case study does not claim to measure Anthropic’s emissions directly. It estimates them, from contracts, sites, on-site generation and marginal grid modelling, and it presents the result as a range. Within those limits, the message is clear: on the commitments in place as of October 2026, the study estimates that Anthropic’s data centres will run largely on fossil power in 2028, with gas at about 87% and coal at 11%, and with a mid-case of 32 million metric tons of CO2 equivalent a year. That is the finding to carry forward, as summarised here, and the uncertainty around it is part of the finding, not an afterthought.